DEWA Accelerates Dubai's Power Network Expansion with Over AED 10 Billion Investment
Dubai Electricity & Water Authority (DEWA) has significantly ramped up investments in the emirate's electricity transmission network, committing over AED 10 billion to support burgeoning demand and future urban developme
Dubai Electricity & Water Authority (DEWA) is proactively expanding its electricity transmission infrastructure, with recent investments in transmission projects surpassing AED 10 billion ($2.7 billion). This strategic push is aimed at addressing Dubai's escalating electricity demand, driven by rapid population growth and new developments.
The utility is currently engaged in constructing a substantial number of new facilities, including 65 new 132kV substations and one 400kV substation. Looking ahead, DEWA has ambitious plans for further expansion, intending to issue tenders for more than 30 additional 132kV substations over the next three years. These plans also encompass extending 340 kilometres of underground transmission cables and building two additional 400kV substations.
Recent Contracts and Commissions
In a recent tender, DEWA received bids from eight companies for a contract to supply, install, test, and commission 132kV cable works across various substations in Dubai. This follows significant activity in the first half of 2026:
- DEWA awarded 21 contracts for 132kV transmission substations.
- Contracts were also awarded for 64km of 132kV cables connecting these substations to the main network, valued at AED 3 billion ($817 million).
- The authority commissioned eight 132kV substations with a combined conversion capacity of 1,200MVA, representing an investment of AED 970 million ($264 million). These projects included 20km of transmission cables.
By the end of June, DEWA reported operating 402 transmission substations, with 374 of these at the 132kV level and the remainder being 400kV substations. This sustained investment highlights Dubai's commitment to robust and reliable utility services.
Questions, answered
- What is DEWA's recent investment in Dubai's electricity transmission network?
- DEWA's investments in transmission projects have **exceeded AED 10 billion ($2.7 billion)**, aimed at meeting rising electricity demand across Dubai.
- How many new substations is DEWA currently building?
- DEWA is currently constructing **65 new 132kV substations and one 400kV substation** as part of its network expansion efforts.
- What are DEWA's future plans for transmission network expansion over the next three years?
- Over the next three years, DEWA plans to issue tenders for **more than 30 additional 132kV substations**, extend **340 kilometres of underground transmission cables**, and build **two 400kV substations**.
- What was the combined value of 132kV cable contracts awarded by DEWA in the first half of 2026?
- In the first half of 2026, DEWA awarded contracts for **64km of 132kV cables** connecting substations to the main network, with a combined value of **AED 3 billion ($817 million)**.
- What was the operational capacity of DEWA's transmission substations by the end of June 2026?
- By the end of June 2026, DEWA had **402 transmission substations in operation**, with **374 of these at the 132kV level** and the remainder being 400kV substations.
This brief was summarised and rewritten by Gaia Living from public reporting. Figures and details reflect the original sources.
More in Infrastructure
- InfrastructureUAE Increases Strategic Investment in African Ports and Resources
- InfrastructureNavi Mumbai Airport Launches International Cargo Service with Sharjah Flight
- InfrastructureSharjah's Khorfakkan Port Launches Direct China Shipping Route with Record Vehicle Shipment
- InfrastructureSaudi Arabia Unveils New 246km Rafha-Hail Road to Boost Regional Connectivity